Pleasant Harbor Marina is looking forward
to getting a New Fuel Dock!
Marine Floats of Tacoma has been building a replacement for "D" dock, including
our fuel dock. We're looking forward to the scheduled install date of Feb
2009, if all goes according to plan. Below are a few photos of the
construction at the Marine Floats Facility.
March 2009 .....almost done!
|
|
|
|
|
|
|
|
|
|
electricians at work
|
|
|
|
Test fire lines
|
|
|
|
|
install fuel controls
|
|
|
|
|
Test fuel pumps YEA!
|
|
|
|
Beautiful New loading area!
|
|
|
|
New picnic area in front of store!
|
|
|
|
New railing (not yet complete)
|
|
|
|
Great Job on bank stabilization!
|
|
|
|
|
Thanks Ray & Danny!
|
|
|
|
New pumps & reels
|
|
|
2/25 & 2/26 2009
2/24/09
demolition and removal of the old fuel dock "D-Dock"
Update 2/18/09
We started removing the
old D-dock (Fuel Dock) today!! By sunset all the fingers were removed and
the half the decking for the landing is gone. The D-dock ramp is now
closed until the new dock & ramp are in place. Please use the A/B dock
ramp to access C, E, & F docks. D-dock will be open for fuel and pumpout
until Monday 2/23 when we will stop service until the new dock is in place.
Update 2/17/09
Here's photos of the new
dock and fuel building. The complete dock should depart Tacoma on Monday
2/23 and arrive at Pleasant Harbor Tuesday afternoon 2/24 if the weather is
good. Things will start happening fast on Wednesday!
Construction Progress as
of 1/27/09
Fuel House will be moved to the end of the dock shallow water finger with grated deck Far end, where fuel house will be Construction of sumps for fuel system
Fuel House will be moved to the end of the dock
|
|
|
Jan 5 - what the deck will look like
|
|
|
|
|
Jan 5 - framing detail
|
|
|
|
Jan 5 - finger ready to go in the water
|
|
|
|
Jan 5 - more fingers
|
|
|
|
|
Jan 5 - part of main dock
|
|
|
|
Jan 5 - main dock section waiting for floatation
|
|
|
|
Jan 5 - float tub installation
|
|
|
|
Jan 5 - flotation tubs
|
|
|
|
12/19 pallets of decking
|
|
|
|
|
|
12/19 finger fabrication
|
|
|
|
12/19 finger fabrication
|
|
|
|
12/19 fingers
|
|
|
|
12/19 floation tubs
|
|
|
|
|
12/19 framing material
|
|
|
|
|
12/19 in the water, getting ready for decking
|
|
|
|